A modern, fast and safe way to the North Coast

July
Signing of the Agreement between DERSA and DER for the duplication of the Plateau Section works
December
Issue of the Preliminary Environmental License (Plateau Section)
April
Publication of the Public Tender in the Official Gazette (Plateau Section)
May
Publication of the Public Service Decree in the Official Gazette, issue of the Priority Installation License and start of the works for the duplication of the Plateau Section
July
Issue of the Priority 2 Installation License (Plateau Section)
August
Issue of the Priority 3 and 4 Installation Licenses (Plateau Section) and of the Preliminary Environmental License – Lots 2, 3, and 4 (Contornos Section)
October
Signing of the Agreement between DERSA and DER, issue of the Preliminary Environmental License - Lot 1, publication of the Public Tender in the Official Gazette, issue of the Priority 1 Installation License - Lots 1 and 2 and start of the works in the Lots 1 and 2 (Contornos Section)
September
Issue of the Priority 1 Installation License – Lot 1 (Contornos Section)
October
Issue of the Priority 1 Installation License – Lot 2 and start of the works in the Lots 1 and 2 (Contornos Section)
December
Start of the works for the implementation of accesses in the properties bordering the highway (Plateau Section) and issue of the Rectified Preliminary Environmental License – Lots 3 and 4 (Contornos Section)
January
Completion of the duplication works of the Plateau Section
February
Issue of the Priority 2 Installation License– Lot 1 (Contornos Section)
March
Issue of the Priority 2 Installation License – Lot 2 (Contornos Section)
April
Start of the works for the implementation of the fauna overpass (Plateau Section)
May
Issue of the Priority 3 Installation License – Lot 2, 3, and 4 (Contornos Section)
June
Issue of the Priority 4 Installation License – Lot 2 and start of the works in the lots 3 and 4 (Contornos Section)
September
Completion of the cycle track of the Plateau Section
October
Issue of the Priority 3 Installation License – Lot 1 (Contornos Section)
November
Start of complementary works: construction of 12 pedestrian overpasses (Plateau Section)
December
Issue of the Priority 5 Installation License– Lots 3 and 4 (Contornos Section)
April
Issue of the Operating License of the Plateau Section
August
Inauguration of the Animal Rehabilitation Center (Jundiaí)
October
Issue of the Priority 6 Installation License – Lots 3 and 4 (Contornos Section)
February
Excavation of the first 1,000 meters of the left lane from the Tunnel 301 – Lot 3 and environmental workshop in the Maria Alice Rangel School (São Sebastião)
March
Workshop "Play Safely" at the Massoko Sone School and Pingo de Gente School (São Sebastião)
April
Excavation of the first 1,000 meters of the right lane from the Tunnel 301 – Lot 3 and Workshop "Play Safely" at the Pônei Azul School (São Sebastião)
May
Training courses to bricklayer, Iron Structure Assembler and Carpenter to near residents to constructions
July
Junction of the excavations from the right lane of the tunnel 102 (side drift) by the north and south tunnel entry - Lot 1 and opening of New Community Center Mário Cândido de Oliveira (Morro do Abrigo – São Sebastião)
August
Beginning of the left lane from tunnel of the excavation Tunnel 402 (São Sebastião) and Environmental workshop at Mestre School (São Sebastião)
September
Project Garoçá - Environmental Workshop at Profª José Maria da Penha Frugoli State School (São Sebastião)
October
Donation 34 housing units in Caraguatatuba, Environmental workshop at Profª José Maria da Penha Frugoli State School (São Sebastião) and Course of frontline tunnel staff (São Sebastião)
October
Meeting of the excavations of the tunnel 301 (São Sebastião)
November
Alignment meeting of the Workshop "Play Safe" with contractors’ social team (São Paulo)
December
Beginning of compensatory planting and other forest restoration practices (São Sebastião, Caraguatatuba and São Luiz do Paraitinga)
Estimated completion date